Pro Tips for Passing a PV System Capacity Test
The primary objective of **ASTM E2848**, *"Standard Test Method for Reporting Photovoltaic Non-Concentrator System Performance,"* is to evaluate how well a photovoltaic (PV) power plant performs in the field compared to its expected output based on a system model. For newcomers, understanding the model and schedule used in capacity testing is crucial.
In this article, I’ll explore some more nuanced aspects of PV capacity testing—such as weather files and shade modeling, commissioning and instrumentation, seasonality and location, and technology and design. By carefully addressing these factors, you can significantly improve your chances of passing the test smoothly.
---
### Weather File & Shade Model
While there are many inputs to a PVsyst model, **weather files** and **shade models** have the most significant impact on long-term energy yield. Since capacity tests are normalized for weather conditions, it’s essential to pay close attention to the shade model. A shade model is not just helpful—it's a requirement. Without it, your PVsyst results may overestimate performance, leading to unrealistic expectations.
Shade models also help identify data points that should be excluded from the test, ensuring you don’t include suboptimal or inaccurate data. Additionally, 3D terrain can influence the average plane-of-array (POA) irradiance, which directly affects the accuracy of the capacity test. If the actual performance doesn't match the model, it's often due to an improperly modeled shading scenario.
---
### Commissioning & Instrumentation
Proper commissioning and accurate instrumentation are critical for successful capacity testing. Before conducting any performance test, the system must be fully commissioned and operating normally. This includes ensuring all components are functional and that there are no outages.
It’s recommended to run at least a **48-hour pre-qualification period** before starting the actual test. During this time, all sensors and instruments should be checked and calibrated. Often, sensors are installed but not properly aligned or calibrated, which can lead to unreliable data during the test.
Key steps in commissioning include verifying POA sensor alignment with global horizontal irradiance (GHI), ensuring temperature sensors are free from obstructions, and confirming that ambient and module temperatures are measured accurately. For POA sensors, placement is key—especially in areas with rolling terrain. The sensor should reflect the true average irradiance across the site, not just the design assumption.
---
### Seasonality & Location
The time of year and project location play a major role in the success of a capacity test. ASTM E2848 outlines acceptable testing conditions, including irradiance levels and the presence of shade or inverter clipping. These factors are often interconnected—low irradiance can mean more shade, while high irradiance can cause inverter power limiting.
Testing windows can vary greatly depending on the region. In winter, for example, daylight hours are limited, and low irradiance or shading may reduce the available testing time. If you lose two hours in the morning and two in the evening, you’re left with only four hours per day. If clipping occurs in the middle of the day, that window could shrink even further, making it difficult to collect the required 50 valid data points.
In regions like the Midwest or Northeast, winter testing might not be practical. It’s better to plan ahead and adjust the testing schedule if construction delays push it into colder months.
---
### Technology & Design
Finally, adapting your testing approach to account for new technologies like **bifacial modules** or **high DC-to-AC ratios** is essential. While ASTM E2848 doesn’t specifically address bifacial systems, you can still perform the test by adding a rear-side POA sensor. This allows you to capture both front and back irradiance, giving a more accurate picture of system performance.
For high DC-to-AC ratio systems, where inverters limit power more than 50% of the time, you may need to modify system operation. Options include disabling trackers or reducing DC capacity temporarily. Whatever method you choose, make sure your model reflects the temporary conditions to avoid discrepancies.
By considering these factors and preparing accordingly, you can ensure a smoother and more accurate PV capacity test.